Exam 4: Budgeting the Project
Exam 1: The World of Project Management70 Questions
Exam 2: The Manager, the Organization, and the Team68 Questions
Exam 3: Planning the Project63 Questions
Exam 4: Budgeting the Project64 Questions
Exam 5: Scheduling the Project63 Questions
Exam 6: Allocating Resources to the Project66 Questions
Exam 7: Monitoring and Controlling the Project72 Questions
Exam 8: Evaluating and Terminating the Project67 Questions
Select questions type
A task is expected to take 20 hours of labor at $25 per hour. The required material cost is $500 and the organization charges 30% of direct labor for overhead. The total task cost is:
(Multiple Choice)
4.8/5
(40)
Explain the concept of Brook's "mythical man month"?
(Not Answered)
This question doesn't have any answer yet
Explain how you would use the shape of a project's life cycle to resolve budget conflicts between a superior and subordinate.
(Not Answered)
This question doesn't have any answer yet
Define the term learning rate.
(Not Answered)
This question doesn't have any answer yet
As a project unfolds, the cost uncertainty increases as the project moves towards completion.
(True/False)
4.9/5
(36)
The first unit required 6 hours. If the industry uses a 90 percent learning rate, how long should the fourth unit take?
(Multiple Choice)
4.9/5
(42)
The budgeting approach based on the collective judgments of top and middle managers is called:
(Multiple Choice)
4.8/5
(30)
Learning curve theory states that performance of labor per unit will improve by a percentage each time production increases by the same percentage.
(True/False)
4.9/5
(39)
After major risk are identified which of the following data should NOT be obtained for analysis
(Multiple Choice)
4.9/5
(36)
Calculating the Tracking Signal can not only reveal if estimates are biased, it can also tell how severe the bias is.
(True/False)
4.7/5
(42)
Traditional organizational budgets are task-oriented, rather than activity-oriented.
(True/False)
4.9/5
(40)
The best approach to handling change in projects is to accept the negative change and take a loss on the project.
(True/False)
4.7/5
(34)
The PMI does not devote much coverage to risk management in the PMBOK
(True/False)
4.8/5
(40)
Showing 41 - 60 of 64