Exam 6: Allocating Resources to the Project

arrow
  • Select Tags
search iconSearch Question
flashcardsStudy Flashcards
  • Select Tags

List and briefly explain five priority rules used to assign preference to activities when allocating scarce resources.

Free
(Not Answered)
This question doesn't have any answer yet
Ask our community

The amount of resources a project can use depends in part on the timing of the allocation.

Free
(True/False)
4.9/5
(41)
Correct Answer:
Verified

True

Pools of like resources from which labor can be added temporarily to projects tend to increase costs for the firm as a whole.

Free
(True/False)
4.7/5
(41)
Correct Answer:
Verified

False

The practice of assigning project team members to multiple projects is called…

(Multiple Choice)
4.8/5
(32)

If resources were not scarce, the resource allocation problem would be concerned solely with cost minimization.

(True/False)
4.9/5
(40)

Good project managers are able to estimate project task times with absolute certainty.

(True/False)
4.8/5
(35)

A resource allocation decision may be intended to avoid a future problem rather than correct a current problem.

(True/False)
4.7/5
(35)

A project that must be completed by a specific time is considered…

(Multiple Choice)
4.8/5
(36)

Projects often compete with each other for the same resources.

(True/False)
4.9/5
(26)

The as late as possible priority rule is considered the standard scheduling rule.

(True/False)
4.7/5
(27)

All projects are carried out under conditions of uncertainty.

(True/False)
4.9/5
(28)

A task has a normal duration of 9 days and a crash duration of 7 days. Its normal cost is $40 and its crash cost is $100. What is the crash cost per day?

(Multiple Choice)
4.8/5
(36)

According to research, the best overall priority rule is…

(Multiple Choice)
4.8/5
(37)

The variance of the normal time can be quite different from the variance of the crash time.

(True/False)
4.9/5
(38)

Resource loading refers to the amounts of specific resources that are scheduled for use on specific activities or projects at specific times.

(True/False)
4.8/5
(40)

Starting the building phase before the design and planning phases is called…

(Multiple Choice)
4.8/5
(38)

What is fast-tracking a project?

(Not Answered)
This question doesn't have any answer yet
Ask our community

Which of the following is not considered a resource?

(Multiple Choice)
5.0/5
(42)

If resources were not scarce, the resource allocation problem would be concerned solely with profit maximization.

(True/False)
4.8/5
(42)

. The shortest duration task first rule minimizes the number of tasks that can be completed by s system in a given time period.

(True/False)
4.8/5
(39)
Showing 1 - 20 of 66
close modal

Filters

  • Essay(0)
  • Multiple Choice(0)
  • Short Answer(0)
  • True False(0)
  • Matching(0)