Exam 5: Scheduling the Project
Exam 1: The World of Project Management52 Questions
Exam 2: The Manager, the Organization, and the Team45 Questions
Exam 3: Planning the Project48 Questions
Exam 4: Budgeting the Project46 Questions
Exam 5: Scheduling the Project46 Questions
Exam 6: Allocating Resources to the Project46 Questions
Exam 7: Monitoring and Controlling the Project45 Questions
Exam 8: Evaluating and Terminating the Project45 Questions
Select questions type
A Gantt chart can NOT depict a critical path,only a PERT/CPM chart can.
(True/False)
4.8/5
(36)
A start-to-finish linkage is the most common way of linking to successive task.
(True/False)
4.9/5
(37)
A project schedule is a project action plan converted into a timetable.
(True/False)
4.8/5
(36)
Technical dependencies are often harder to see on a Gantt chart than on a PERT/CPM network.
(True/False)
4.7/5
(25)
Which of the following is NOT an element of the Gantt chart?
(Multiple Choice)
4.9/5
(29)
.Milestones are not depended upon the predecessor activities in the project plan.
(True/False)
4.7/5
(34)
Which of the following linkages is used to start two or more activities at the same time?
(Multiple Choice)
4.9/5
(43)
A big advantage of AON networks is that they are easier to draw.
(True/False)
4.9/5
(31)
AON and AOA networks can both be used to depict any project network.
(True/False)
4.9/5
(25)
"Merger" is a term used to describe the situation in which two or more paths in a network join together.
(True/False)
4.8/5
(39)
The actual project duration will be known with certainty after the project is completed.
(True/False)
4.8/5
(35)
The simulation approach is generally preferred over the statistical method.
(True/False)
4.8/5
(46)
The start-to-finish linkage is used in situations where is it desirable for two or more activities to finish at the same time.
(True/False)
4.9/5
(29)
If task duration estimates are carefully made,the project manager needs to only examine the critical path when conducting a risk analysis.
(True/False)
5.0/5
(37)
Technical dependencies are generally easier to see on a Gantt chart than on PERT/CPM networks.
(True/False)
4.7/5
(33)
The shortest time to complete a network is equal to the duration of the longest path through the network.
(True/False)
4.8/5
(31)
Which of the following terms is most closely associated with a task required by the project?
(Multiple Choice)
4.8/5
(32)
Showing 21 - 40 of 46
Filters
- Essay(0)
- Multiple Choice(0)
- Short Answer(0)
- True False(0)
- Matching(0)