A Gantt chart can NOT depict a critical path,only a PERT/CPM chart can.

(True/False)
4.8/5
(36)

A start-to-finish linkage is the most common way of linking to successive task.

(True/False)
4.9/5
(37)

An event is a series of connected activities.

(True/False)
4.9/5
(32)

A project schedule is a project action plan converted into a timetable.

(True/False)
4.8/5
(36)

Technical dependencies are often harder to see on a Gantt chart than on a PERT/CPM network.

(True/False)
4.7/5
(25)

Which of the following is NOT an element of the Gantt chart?

(Multiple Choice)
4.9/5
(29)

.Milestones are not depended upon the predecessor activities in the project plan.

(True/False)
4.7/5
(34)

Which of the following linkages is used to start two or more activities at the same time?

(Multiple Choice)
4.9/5
(43)

Slack is calculated as?

(Multiple Choice)
4.7/5
(36)

A big advantage of AON networks is that they are easier to draw.

(True/False)
4.9/5
(31)

The difference between LFT and EFT is called slack.

(True/False)
4.9/5
(42)

AON and AOA networks can both be used to depict any project network.

(True/False)
4.9/5
(25)

"Merger" is a term used to describe the situation in which two or more paths in a network join together.

(True/False)
4.8/5
(39)

The actual project duration will be known with certainty after the project is completed.

(True/False)
4.8/5
(35)

The simulation approach is generally preferred over the statistical method.

(True/False)
4.8/5
(46)

The start-to-finish linkage is used in situations where is it desirable for two or more activities to finish at the same time.

(True/False)
4.9/5
(29)

If task duration estimates are carefully made,the project manager needs to only examine the critical path when conducting a risk analysis.

(True/False)
5.0/5
(37)

Technical dependencies are generally easier to see on a Gantt chart than on PERT/CPM networks.

(True/False)
4.7/5
(33)

The shortest time to complete a network is equal to the duration of the longest path through the network.

(True/False)
4.8/5
(31)

Which of the following terms is most closely associated with a task required by the project?

(Multiple Choice)
4.8/5
(32)
Showing 21 - 40 of 46