Exam 3: Managing Systems Projects

arrow
  • Select Tags
search iconSearch Question
flashcardsStudy Flashcards
  • Select Tags

MATCHING Identify the letter of the choice that best matches the phrase or definition. a.project management f.weight b.project coordinator g.bottom-up technique c.project leader h.dependent d.milestone i.concurrent e.constraint j.predecessor -In discussing PERT/CPM charts, you discuss the types of task patterns that can occur in a project schedule. You give an example of two tasks, A and B, that can both begin as soon as task C is finished. Which of the following is NOT a true statement about tasks A and B?

(Multiple Choice)
4.9/5
(28)

In GanttProject, unlike in Microsoft Project, you create tasks and durations, indicate dependencies, and assign resources.

(True/False)
4.9/5
(33)

A risk ____ plan is a proactive effort to anticipate a risk and describe an action plan to deal with it.

(Multiple Choice)
4.8/5
(31)

  -A(n) ____________________ is a recognizable reference point that can be used to monitor progress and manage a project. -A(n) ____________________ is a recognizable reference point that can be used to monitor progress and manage a project.

(Short Answer)
4.9/5
(37)

Microsoft claims that Microsoft Project has the capability of ____.

(Multiple Choice)
4.9/5
(28)

A PERT/CPM chart does not show the project as a network diagram with tasks connected by arrows.

(True/False)
5.0/5
(46)

A ____ path includes all tasks that are vital to the project schedule.

(Multiple Choice)
4.8/5
(32)

PERT/CPM is called a(n) ____ technique, because it analyzes a large, complex project as a series of individual tasks.

(Multiple Choice)
4.7/5
(43)

When two or more concurrent tasks depend on a single prior task, each of the concurrent tasks is called a predecessor task.

(True/False)
4.8/5
(36)

MATCHING Identify the letter of the choice that best matches the phrase or definition. a.project management f.weight b.project coordinator g.bottom-up technique c.project leader h.dependent d.milestone i.concurrent e.constraint j.predecessor -You show Mauricio the formula that project managers often use for estimating the duration of a task. Which of the following is NOT one of factors in that formula?

(Multiple Choice)
4.7/5
(32)

The purpose of quantitative risk analysis is to understand the actual impact in terms of dollars, time, project scope, or quality. _________________________

(True/False)
4.8/5
(36)

Gantt charts often are included in progress reports to show project status graphically. _________________________

(True/False)
4.8/5
(43)

Project management software can highlight the series of tasks that form the critical path.

(True/False)
4.8/5
(34)

MATCHING Identify the letter of the choice that best matches the phrase or definition. a.project management f.weight b.project coordinator g.bottom-up technique c.project leader h.dependent d.milestone i.concurrent e.constraint j.predecessor -Tasks that must be completed before another task can start.

(Short Answer)
5.0/5
(36)

A(n) ____ chart displays complex task patterns and relationships.

(Multiple Choice)
4.9/5
(35)

When several tasks can take place at the same time, each is called a sequential task.

(True/False)
4.8/5
(34)

If you do not have previous experience to measure a project in a given environment, you could design a prototype or pilot system to gain technical and cost estimating experience.

(True/False)
4.9/5
(41)

MATCHING Identify the letter of the choice that best matches the phrase or definition. a.project management f.weight b.project coordinator g.bottom-up technique c.project leader h.dependent d.milestone i.concurrent e.constraint j.predecessor -The process of planning, scheduling, monitoring, and reporting on the development of an information system.

(Short Answer)
4.7/5
(44)

MATCHING Identify the letter of the choice that best matches the phrase or definition. a.project management f.weight b.project coordinator g.bottom-up technique c.project leader h.dependent d.milestone i.concurrent e.constraint j.predecessor -Handles the administrative responsibilities for the development team.

(Short Answer)
4.9/5
(36)

  -The accompanying figure shows task ____, which simplify a complex task by combining several activities. -The accompanying figure shows task ____, which simplify a complex task by combining several activities.

(Multiple Choice)
4.9/5
(36)