A unit of work should appear at only one place in the WBS.

Free
(True/False)
4.8/5
(35)
Correct Answer:
Verified

True

_____ is the difference between planned and actual performance.

Free
(Short Answer)
4.8/5
(39)
Correct Answer:
Verified

Variance

Which of the following is recommended for the creation of a good WBS?

Free
(Multiple Choice)
4.9/5
(35)
Correct Answer:
Verified

B

A work package represents one component of the product that the project aims to deliver.

(True/False)
4.8/5
(44)

_____ refers to all the work involved in creating the products of the project and the processes used to create them.

(Short Answer)
4.8/5
(33)

What are some of the suggestions for improving the requirements process?

(Essay)
4.9/5
(41)

Many organizations provide different guidelines and templates for developing WBSs.

(True/False)
4.8/5
(32)

A(n) ____ is a task at the lowest level of the WBS.

(Multiple Choice)
4.8/5
(36)

The main outputs of scope definition are the _____ and project document updates.

(Short Answer)
4.7/5
(42)

Creating the WBS is a subprocess associated with the _____ process in project scope management.

(Multiple Choice)
4.8/5
(32)

_____ involves controlling changes to the project scope while keeping project goals and business strategy in mind.

(Short Answer)
4.8/5
(32)

The scope baseline in a WBS consists of the requirements documentation and enterprise environmental factors.

(True/False)
4.9/5
(33)

Some organizations prescribe the form and content for WBSs for particular projects. These are known as _____.

(Short Answer)
4.9/5
(35)

Project scope management includes the processes involved in defining and controlling what is or is not included in a project.

(True/False)
4.8/5
(35)

Describe the process of scope verification.

(Essay)
4.8/5
(35)

In the _____ approach, team members first identify as many specific tasks related to the project as possible and then aggregate the specific tasks and organize them into summary activities, or higher levels in the WBS.

(Multiple Choice)
4.8/5
(34)

A work package is a task at the _____ level of the WBS.

(Short Answer)
4.8/5
(31)

The _____ approach for constructing a WBS involves refining the work into greater and greater levels of detail.

(Multiple Choice)
4.8/5
(40)

_____ refer to "conditions or capabilities that must be met by the project or present in the product, service, or result to satisfy an agreement or other formally imposed specification."

(Short Answer)
4.8/5
(46)

The main tool for performing scope validation is _____ and group decision making techniques.

(Short Answer)
4.7/5
(33)