Exam 5: Project Scope Management
Exam 1: Introduction to Project Management96 Questions
Exam 2: The Project Management and Information Technology Context89 Questions
Exam 3: The Project Management Process Groups: A Case Study83 Questions
Exam 4: Project Integration Management83 Questions
Exam 5: Project Scope Management77 Questions
Exam 6: Project Time Management102 Questions
Exam 7: Project Cost Management102 Questions
Exam 8: Project Quality Management81 Questions
Exam 9: Project Human Resource Management89 Questions
Exam 10: Project Communications Management74 Questions
Exam 11: Project Risk Management79 Questions
Exam 12: Project Procurement Management83 Questions
Exam 13: Project Stakeholder Management50 Questions
Select questions type
The scope management plan can be informal and broad or formal and detailed, based on the needs of the project.
(True/False)
5.0/5
(29)
_____ involves formal acceptance of the completed project scope by the stakeholders.
(Multiple Choice)
4.9/5
(37)
In the _____ approach to creating a WBS, team members first identify as many specific tasks related to the project as possible.
(Short Answer)
4.8/5
(35)
Tasks in a WBS that are decomposed into smaller tasks are called _____ tasks.
(Short Answer)
4.9/5
(34)
_____ includes the processes involved in defining and controlling what work is or is not included in a project.
(Short Answer)
4.9/5
(30)
The main technique used in creating a WBS is _____, which involves subdividing project deliverables into smaller pieces.
(Multiple Choice)
4.9/5
(44)
The _____ approach for constructing a WBS starts with the largest items of the project and breaks them into subordinate items.
(Multiple Choice)
4.9/5
(34)
Many information technology projects also require detailed functional and design specifications for developing software, which also should be referenced in the detailed scope statement.
(True/False)
4.8/5
(42)
The project scope statement, stakeholder requirements documentation, and organizational process assets are the primary inputs for creating a WBS.
(True/False)
4.8/5
(42)
_____ is a process for identifying and modeling business events, who initiated them, and how the system should respond to them.
(Multiple Choice)
4.8/5
(34)
A(n) _____ is a table that lists requirements, their various attributes, and the status of the requirements to ensure that all are addressed.
(Multiple Choice)
4.9/5
(39)
The main outputs of _____are the project scope statement and updates to project documents.
(Short Answer)
4.7/5
(45)
A(n) _____ is a deliverable-oriented grouping of the work involved in a project that defines the total scope of the project.
(Multiple Choice)
4.9/5
(44)
_____ involves reviewing the project charter, requirements documents, and organizational process assets to create a scope statement, adding more information as requirements are developed and change requests are approved.
(Multiple Choice)
4.9/5
(39)
Information from the project charter provides a basis for further defining the project scope.
(True/False)
4.8/5
(33)