Exam 3: Managing Systems Projects
Exam 1: Introduction to Systems Analysis and Design80 Questions
Exam 2: Analyzing the Business Case81 Questions
Exam 3: Managing Systems Projects78 Questions
Exam 4: Requirements Modeling98 Questions
Exam 5: Data and Process Modeling84 Questions
Exam 6: Object Modeling78 Questions
Exam 7: Development Strategies82 Questions
Exam 8: User Interface Design82 Questions
Exam 9: Data Design86 Questions
Exam 10: System Architecture78 Questions
Exam 11: Managing Systems Implementation81 Questions
Exam 12: Managing Systems Support and Security81 Questions
Exam 13: Toolkit A: The Systems Analysts Toolkit45 Questions
Exam 14: Toolkit B: Case Tools44 Questions
Exam 15: Toolkit C: Financial Analysis Tools45 Questions
Exam 16: Toolkit D: Internet Resource Tools44 Questions
Select questions type
Matching
Identify the letters of the choices that best match the phrases or definitions.
-Developed by the U.S. Navy to manage very complex projects
(Multiple Choice)
4.9/5
(32)
Mauricio estimates that the first module of the project could be completed in as few as 15 days or could take as many as 25 days, but most likely will require 20 days. Determine the expected task duration.
(Multiple Choice)
4.8/5
(31)
Matching
Identify the letters of the choices that best match the phrases or definitions.
-Defines the tasks that can start at the same time
(Multiple Choice)
4.8/5
(29)
If team members lack experience with certain aspects of the required technology, temporary help might be obtained from IT consultants or part-time staff.
(True/False)
4.9/5
(31)
A(n) _____ is any work that has a beginning and an end and requires the use of company resources such as people, time, or money.
(Multiple Choice)
5.0/5
(31)
A _____ displays the same information as the Gantt chart, including task dependencies, but uses task boxes to include much more detail.
(Multiple Choice)
4.9/5
(27)
_____ lists each risk and assesses the likelihood that it could affect a project.
(Multiple Choice)
5.0/5
(39)
Program Evaluation Review Technique (PERT)/Critical Path Method (CPM) and Gantt charts are mutually exclusive techniques.
(True/False)
4.8/5
(40)
The purpose of quantitative risk analysis is to understand the actual impact of a risk in terms of dollars, time, project scope, or quality.
(True/False)
4.8/5
(31)
Using a work breakdown structure (WBS) allows one to manage a project as one large task.
(True/False)
4.9/5
(33)
Mauricio has decided to use a project management tool for this project. He wants the tool to be free and cloud-based so that there is no need for software to be installed. Help Mauricio in identifying the project management tool that best fits the purpose.
(Multiple Choice)
4.8/5
(48)
Structured walk-throughs take place throughout the SDLC and are called _____ reviews, depending on the phase in which they occur.
(Multiple Choice)
4.9/5
(35)
When two or more concurrent tasks depend on a single prior task, each of the concurrent tasks is called a(n) _____.
(Multiple Choice)
4.8/5
(31)
In a Program Evaluation Review Technique (PERT)/Critical Path Method (CPM) chart, each rectangular box, called a task box, has five sections that contain important information about a task.
(True/False)
4.8/5
(30)
Using a(n) _____, a project manager can convert task start and finish times to actual dates by laying out the entire project on a calendar.
(Multiple Choice)
4.8/5
(35)
A _____ is a review of a project team member's work by other members of a team.
(Multiple Choice)
4.8/5
(25)
Quantitative risk analysis evaluates each risk by estimating the probability that it will occur and the degree of impact.
(True/False)
4.9/5