Exam 3: Managing Systems Projects
Exam 1: Introduction to Systems Analysis and Design80 Questions
Exam 2: Analyzing the Business Case81 Questions
Exam 3: Managing Systems Projects78 Questions
Exam 4: Requirements Modeling98 Questions
Exam 5: Data and Process Modeling84 Questions
Exam 6: Object Modeling78 Questions
Exam 7: Development Strategies82 Questions
Exam 8: User Interface Design82 Questions
Exam 9: Data Design86 Questions
Exam 10: System Architecture78 Questions
Exam 11: Managing Systems Implementation81 Questions
Exam 12: Managing Systems Support and Security81 Questions
Exam 13: Toolkit A: The Systems Analysts Toolkit45 Questions
Exam 14: Toolkit B: Case Tools44 Questions
Exam 15: Toolkit C: Financial Analysis Tools45 Questions
Exam 16: Toolkit D: Internet Resource Tools44 Questions
Select questions type
A(n) _____ is a series of tasks that, if delayed, would affect the completion date of the overall project.
Free
(Multiple Choice)
4.7/5
(41)
Correct Answer:
A
A continuous risk-tracking process can _____.
Free
(Multiple Choice)
4.9/5
(41)
Correct Answer:
A
A(n) _____ is an event that could affect a project negatively.
Free
(Multiple Choice)
4.8/5
(35)
Correct Answer:
D
If any task along a critical path falls behind schedule, the entire project will be delayed.
(True/False)
4.7/5
(32)
System developers can initiate a formal project as early as the preliminary investigation stage, or later on, as analysis, design, and implementation activities occur.
(True/False)
4.8/5
(33)
Program Evaluation Review Technique (PERT) is a _____ technique because it analyzes a large, complex project as a series of individual tasks.
(Multiple Choice)
4.8/5
(36)
A _____ negotiates with users who might have conflicting requirements or want changes that would require additional time or expense.
(Multiple Choice)
4.9/5
(41)
Generally, systems analysts review the work of other systems analysts, and programmers review the work of other programmers, as a form of peer review, in structured walk-throughs.
(True/False)
4.8/5
(44)
_____, a human resource issue, is a possible cause of cost overruns in an organization.
(Multiple Choice)
5.0/5
(32)
The first step in creating a work breakdown structure (WBS) is to _____.
(Multiple Choice)
4.9/5
(31)
Matching
Identify the letters of the choices that best match the phrases or definitions.
-Handles the administrative responsibilities for a development team
(Multiple Choice)
4.8/5
(43)
A(n) _____ is a recognizable reference point that can be used to monitor progress.
(Multiple Choice)
4.9/5
(41)
Project managers always must be aware of the _____, so they can monitor the vital tasks and keep a project on track.
(Multiple Choice)
4.9/5
(27)
Matching
Identify the letters of the choices that best match the phrases or definitions.
-A condition, restriction, or requirement that a system must satisfy
(Multiple Choice)
4.8/5
(34)
The prior experience method to make time and cost estimates works best for large projects.
(True/False)
4.9/5
(36)
Matching
Identify the letters of the choices that best match the phrases or definitions.
-Usually a senior systems analyst or an IT department manager, if the project is large
(Multiple Choice)
4.8/5
(38)
In most systems analysis tasks, time and people are interchangeable.
(True/False)
4.9/5
(40)
A _____ is a series of events and activities with no slack time.
(Multiple Choice)
4.9/5
(34)