Exam 13: Jitlean Production
Which of the following is NOT an element of Lean production?
B
Recent developments in Lean thinking have combined these principles with Six Sigma and with supply chain management.Pick either one of these programs and describe its elements.Then provide an example from current business news of an operation or supply chain that has embraced these principles.
Examples will vary.
Lean Six Sigma combines the organizational elements and tools of Six Sigma,with Lean's focus on waste reduction.As Paul Mullenhour and Jamie Flinchbaugh put it,"Lean encourages action along a broad front by empowering people at all levels to contribute.This allows organizations to welcome challenges and implement improvement initiatives...Six Sigma brings the discipline of define,measure,analyze,improve and control,as well as the rigor of statistical analysis,to identify a root cause,sustain improvement and provide the solid measurements that create a balanced scorecard."
Some practitioners and researchers have moved beyond Lean production to what can be called Lean supply chain management.In a nutshell,Lean supply chain management seeks to minimize the level of resources required to carry out all supply chain activities.Lean principles are applied to eliminate waste in a firm's sourcing and logistics activities,as well as within the firm's internal operations.But it doesn't end there.The Lean philosophy is applied to all relevant flows - physical,informational,and monetary - and,where possible,to supply chain partners.This means that firms might need to work closely with key partners to eliminate waste within their operations.
In the water and rocks analogy for lean:
B
For a kanban system to work properly,demand rates must be relatively stable,and interruptions must be minimized.
________ could result in workers from one company working to solve production issues for a company from which they purchase components.
A manufacturer waits to produce until they have an order from a customer.This type of production system is called ________.
A reduction in inventory levels forces a company to address poor manufacturing practices.
Consider the adjacent work stations in this two card Kanban system.There is a production card located in the box labeled Outgoing Parts B.Work Center 3 pulls the parts from Work Center 2.Where does the production card go? 

Use this material requirements planning record to explain how kanbans and MRP can be used together.This plant operates on a 40-hour week,and uses a 10% safety factor on a container size of 20 units with a half-day turnaround time on a container.What features of each system should be used and for what purposes?


Describe any five of the wastes and their causes identified by the lean philosophy.
Consider the adjacent work stations in this two card Kanban system.Work Center 3 has just pulled the Incoming Parts C box to their work station.Which of these statements is best? 

Two modules are used to feed the final assembly station on an assembly line.The final assembly station must produce 250 units in an eight-hour day.Each finished unit needs two module A's and 3 module B's.The factory uses a standard sized container that can hold 25 module A's or 35 module B's.It takes 2 hours to fill and move a container of module A's,but only 90 minutes to fill and move a container of module B's.If both module assembly processes have safety factors of 15%,how many containers should be used for each? How many hours of demand will this satisfy?
The term just-in-time production is used synonymously with the term Lean production.
The ability of a process to produce quality output is unknown and the time to ship the output to a customer is highly variable.The combination of these two factors will lead to the waste of waiting.
Under two-card kanban system rules,each box of raw material must have a(n)________,while each box of finished goods must have a(n)________.
Olivia has had enough of the theoretical equations and rejects the higher math needed to calculate the number of kanbans for her system.One approach that some organizations take in lieu of the kanban equation is to: