Exam 10: Project Analysis

arrow
  • Select Tags
search iconSearch Question
flashcardsStudy Flashcards
  • Select Tags

Petroleum Inc.(PI)controls offshore oil leases.It is considering the construction of a deep-sea oil rig at a cost of $500 million.The price of oil is $100/bbl.and extraction costs are $50/bbl.PI expects costs to remain constant.The rig will produce an estimated 1,200,000 bbl.per year forever.The risk-free rate is 10% per year,which is also the cost of capital.(Ignore taxes).Suppose that oil prices are uncertain and are equally likely to be $120/bbl.or $80/bbl.next year.Calculate today's NPV of the project if it were postponed by one year.

Free
(Multiple Choice)
4.9/5
(34)
Correct Answer:
Verified

B

Adding a fudge factor to the cost of capital will penalize longer-term projects more due to compounding.

Free
(True/False)
4.8/5
(37)
Correct Answer:
Verified

True

Monte Carlo simulation is likely to be most useful:

Free
(Multiple Choice)
4.9/5
(36)
Correct Answer:
Verified

A

Which of the following does NOT represent an option to abandon a project?

(Multiple Choice)
4.8/5
(32)

You obtain the following data for year 1: Revenue = $43; Variable costs = $30; Depreciation = $3; Tax rate = 30%.Calculate the operating cash flow for the project for year 1.

(Multiple Choice)
4.8/5
(35)

A project requires an initial investment in equipment of $90,000 and then requires an initial investment in working capital of $10,000 (at t = 0).You expect the project to produce sales revenue of $120,000 per year for three years.You estimate manufacturing costs at 60% of revenues.(Assume all revenues and costs occur at year-end,i.e.,t = 1,t = 2,and t = 3.)The equipment depreciates using straight-line depreciation over three years.At the end of the project,the firm can sell the equipment for $10,000 and also recover the investment in net working capital.The corporate tax rate is 30% and the cost of capital is 15%.What is the NPV of the project if the revenues were higher by 10% and the costs were 65% of the revenues?

(Multiple Choice)
4.9/5
(30)

The Solar Calculator Company proposes to invest $5 million in a new calculator-making plant that will depreciate on a straight-line basis.Fixed costs are $2 million per year.A calculator costs $5 per unit to manufacture and sells for $20 per unit.If the plant lasts for three years and the cost of capital is 12%,what is the accounting break-even level of annual sales? (Assume no taxes.)

(Multiple Choice)
4.7/5
(32)

You are planning to produce a new action figure called "Hillary".However,you are very uncertain about the demand for the product.If it is a hit,you will have net cash flows of $50 million per year for three years (starting next year,i.e.,at t = 1).If it fails,you will only have net cash flows of $10 million per year for two years (also starting next year).There is an equal chance that it will be a hit or failure (probability = 50%).You will not know whether it is a hit or a failure until the first year's cash flows are in,i.e.,at t = 1.You have to spend $80 million immediately for equipment and the rights to produce the figure.If you can sell your equipment for $60 million once the first year's cash flows are received,calculate the value of the abandonment option.(The discount rate is 10%.)

(Multiple Choice)
4.8/5
(34)

Petroleum Inc.(PI)controls off-shore oil leases.It is considering the construction of a deep-sea oil rig at a cost of $500 million.The price of oil is $100/bbl.and extraction costs are $50/bbl.PI expects costs to remain constant.The rig will produce an estimated 1,200,000 bbl.per year forever.The risk-free rate is 10% per year,which is also the cost of capital.(Ignore taxes).Suppose that oil prices are uncertain and are equally likely to be $120/bbl.or $80/bbl.next year. Suppose that PI has the option to postpone the project by one year.Calculate the value of the real option to postpone the project for one year.

(Multiple Choice)
4.9/5
(31)

A project requires an initial investment of $150.Your research generates the following estimates of revenues and costs: A project requires an initial investment of $150.Your research generates the following estimates of revenues and costs:    The cost of capital equals 10%.Assume that the cash flows occur in perpetuity.What does a sensitivity analysis of NPV (without taxes)show? (Answers appear in order: [Pessimistic,Most Likely,Optimistic].) The cost of capital equals 10%.Assume that the cash flows occur in perpetuity.What does a sensitivity analysis of NPV (without taxes)show? (Answers appear in order: [Pessimistic,Most Likely,Optimistic].)

(Multiple Choice)
4.8/5
(26)

The following are drawbacks of sensitivity analysis EXCEPT:

(Multiple Choice)
4.8/5
(46)

A project requires an initial investment in equipment of $90,000 and then requires an initial investment in working capital of $10,000 (at t = 0).You expect the project to produce sales revenue of $120,000 per year for three years.You estimate manufacturing costs at 60% of revenues.(Assume all revenues and costs occur at year-end,i.e.,t = 1,t = 2,and t = 3.)The equipment depreciates using straight-line depreciation over three years.At the end of the project,the firm can sell the equipment for $10,000 and also recover the investment in net working capital.The corporate tax rate is 30% and the cost of capital is 12%. Calculate the NPV of the project:

(Multiple Choice)
4.8/5
(40)

After completing a project analysis,an analyst should rely on which tool to make a final recommendation on the project?

(Multiple Choice)
4.8/5
(36)

A project requires an initial investment in equipment of $90,000 and then requires an initial investment in working capital of $10,000 (at t = 0).You expect the project to produce sales revenue of $120,000 per year for three years.You estimate manufacturing costs at 60% of revenues.(Assume all revenues and costs occur at year-end,i.e.,t = 1,t = 2,and t = 3.)The equipment depreciates using straight-line depreciation over three years.At the end of the project,the firm can sell the equipment for $10,000 and also recover the investment in net working capital.The corporate tax rate is 30% and the cost of capital is 15%.Calculate the NPV of the project:

(Multiple Choice)
4.8/5
(41)

Generally,postaudits are conducted for large projects:

(Multiple Choice)
4.8/5
(33)

The Financial Calculator Company proposes to invest $12 million in a new calculator-making plant.Fixed costs are $3 million per year.A financial calculator costs $10 per unit to manufacture and sells for $30 per unit.If the plant lasts for four years and the cost of capital is 20%,what is the break-even level of annual sales? (Assume that revenues and costs occur at the end of each year.Assume no taxes.)Round to the nearest 1,000 units.

(Multiple Choice)
4.8/5
(32)

A project has an initial investment of 100.You have come up with the following estimates of the project's cash flows: A project has an initial investment of 100.You have come up with the following estimates of the project's cash flows:    Suppose the cash flows are perpetuities and the cost of capital is 10%.What does a sensitivity analysis of NPV (no taxes)show? (Answers appear in order: [Pessimistic,Most Likely,Optimistic].) Suppose the cash flows are perpetuities and the cost of capital is 10%.What does a sensitivity analysis of NPV (no taxes)show? (Answers appear in order: [Pessimistic,Most Likely,Optimistic].)

(Multiple Choice)
4.7/5
(34)

Which of the following simulation outputs is likely to be most useful and easy to interpret? The output shows the distribution(s)of the project's:

(Multiple Choice)
4.7/5
(40)

A project requires an initial investment in equipment of $90,000 and then requires an initial investment in working capital of $10,000 (at t = 0).You expect the project to produce sales revenue of $120,000 per year for three years.You estimate manufacturing costs at 60% of revenues.(Assume all revenues and costs occur at year-end,i.e.,t = 1,t = 2,and t = 3.)The equipment depreciates using straight-line depreciation over three years.At the end of the project,the firm can sell the equipment for $10,000.The corporate tax rate is 30% and the cost of capital is 16.5%.Calculate the NPV of the project.

(Multiple Choice)
4.8/5
(36)

Which of the following statements most appropriately describes scenario analysis?

(Multiple Choice)
4.9/5
(40)
Showing 1 - 20 of 75
close modal

Filters

  • Essay(0)
  • Multiple Choice(0)
  • Short Answer(0)
  • True False(0)
  • Matching(0)