Exam 18: Statistical Applications in Quality Management
Exam 1: Defining and Collecting Data145 Questions
Exam 2: Organising and Visualising Data203 Questions
Exam 3: Numerical Descriptive Measures147 Questions
Exam 4: Basic Probability168 Questions
Exam 5: Some Important Discrete Probability Distributions172 Questions
Exam 6: The Normal Distribution and Other Continuous Distributions190 Questions
Exam 7: Sampling Distributions133 Questions
Exam 8: Confidence Interval Estimation186 Questions
Exam 9: Fundamentals of Hypothesis Testing: One-Sample Tests180 Questions
Exam 10: Hypothesis Testing: Two-Sample Tests175 Questions
Exam 11: Analysis of Variance148 Questions
Exam 12: Simple Linear Regression207 Questions
Exam 13: Introduction to Multiple Regression269 Questions
Exam 14: Time-Series Forecasting and Index Numbers201 Questions
Exam 15: Chi-Square Tests134 Questions
Exam 16: Multiple Regression Model Building93 Questions
Exam 17: Decision Making106 Questions
Exam 18: Statistical Applications in Quality Management119 Questions
Exam 19: Further Non-Parametric Tests50 Questions
Select questions type
The Cpk is a one-sided specification limit.
Free
(True/False)
4.8/5
(30)
Correct Answer:
False
Variation signalled by individual fluctuations or patterns in the data is called _______.
Free
(Multiple Choice)
4.9/5
(43)
Correct Answer:
A
Cpk > 1 indicates that the process average is exactly three standard deviations away from the closest specification limit.
Free
(True/False)
4.9/5
(38)
Correct Answer:
False
Instruction 18-2
A local newspaper has 10 delivery boys who each deliver the morning paper to 50 customers every day. The owner decides to record the number of papers delivered on time for a 10-day period and construct a p chart to see whether the percentage is too erratic.
Day Number of Papers Deliverd on Time 1 46 2 45 3 46 4 45 5 43 6 48 7 46 8 49 9 48 10 47
-Referring to Instruction 18-2,what is the numerical value of the centre line for the p chart?
(Multiple Choice)
4.7/5
(34)
Instruction 18-11
Recently, a university switched to a new type of computer-based registration. The registrar is concerned with the amount of time students are spending on the computer registering under the new system. She decides to randomly select eight students on each of the 12 days of the registration and determine the time each spends on the computer registering. The range, mean, and standard deviation of the times required to register are in the table that follows.
Day Range Mean Std. Dev 1 10 5.250 3.4949 2 31 15.250 10.3060 3 13 20.375 4.9262 4 21 22.875 8.3911 5 35 8.500 11.3767 6 18 7.875 6.9372 7 25 11.250 8.5815 8 30 7.875 9.5235 9 17 10.250 6.3640 10 22 9.500 7.8740 11 27 7.875 8.7086 12 26 12.875 9.3723
-Referring to Instruction 18-11,the chart is to be used for the time required to register.One way to obtain the control limits is to take the grand mean and add and subtract the product of A2 times the average of the sample ranges.For this data set,the value of A2 is _______
(Short Answer)
4.9/5
(38)
Special or assignable causes of variation are signalled by individual fluctuations or patterns in the data.
(True/False)
4.7/5
(32)
Instruction 18-10
A supplier of silicone sheets for producers of computer chips wants to evaluate her manufacturing process. She takes a sample size of five from each day's output and counts the number of blemishes on each silicone sheet. The results from 20 days of such evaluations are presented below. She also decides that the upper specification limit is 10 blemishes.
Day 1 2 3 4 5 Mean Range 1 8 10 14 6 5 8.6 9 2 8 13 6 6 10 8.6 7 3 10 12 7 7 9 9.0 5 4 5 9 12 7 10 8.6 7 5 8 3 8 9 10 7.6 7 6 9 7 9 6 9 8.0 3 7 10 10 5 7 6 7.6 5 8 10 9 10 6 5 8.0 5 9 6 10 6 9 9 8.0 4 10 6 9 8 6 8 7.4 3 11 8 5 6 10 10 7.8 5 12 6 4 7 7 12 7.2 8 13 7 5 7 6 9 6.8 4 14 5 8 8 7 6 6.8 3 15 7 12 10 6 10 9.0 6 16 7 11 4 7 8 7.4 7 17 8 4 5 4 7 5.6 4 18 11 4 11 11 10 9.4 7 19 6 10 6 10 10 8.4 4 20 6 12 12 6 8 8.8 6
-Referring to Instruction 18-10,an R chart is to be constructed for the number of blemishes.The centre line of this R chart is located at _______.
(Short Answer)
4.9/5
(36)
Instruction 18-5
The maker of a packaged candy wants to evaluate the quality of her production process. On each of 16 consecutive days, she samples 600 bags of candy and determines the number in each day's sample that she considers to be of poor quality. The data that she developed follow.
Day Number Poor Proportion Poor 1 33 0.0550000 2 29 0.0483333 3 31 0.0516667 4 32 0.0533333 5 43 0.0716667 6 45 0.0750000 7 46 0.0766667 8 48 0.0800000 9 48 0.0800000 10 46 0.0766667 11 28 0.0466667 12 32 0.0533333 13 28 0.0466667 14 32 0.0533333 15 31 0.0516667 16 24 0.0400000
-Referring to Instruction 18-5,a p control chart is to be constructed for these data.The lower control limit is _______,while the upper control limit is _______.
(Short Answer)
4.9/5
(31)
Instruction 18-1
Below is the number of defective items from a production line over 20 consecutive morning shifts.
Day Nonconf. Day Nonconf. 1 26 11 22 2 27 12 26 3 23 13 21 4 21 14 22 5 26 15 19 6 20 16 17 7 35 17 21 8 30 18 18 9 21 19 16 10 25 20 17 Note: Nonconf. = Nonconformances
-Referring to Instruction 18-1,based on the c chart,there appears to be a special cause of variation in the process.
(True/False)
4.8/5
(29)
The control limits are based on the standard deviation of the process.
(True/False)
4.8/5
(30)
Instruction 18-12
The manufacturer of canned food constructed control charts and analysed several quality characteristics. One characteristic of interest is the weight of the filled cans. The lower specification limit for weight is 2.95 kg. The table below provides the range and mean of the weights of five cans tested every 15 minutes during a day's production.
Number XBar Range Number XBar Range 1 3.05072 0.0215 16 3.04646 0.073 2 3.01228 0.087 17 3.03868 0.0696 3 3.03558 0.0851 18 3.03338 0.0329 4 3.01014 0.0674 19 3.03322 0.0455 5 3.00858 0.0983 20 3.05078 0.0215 6 3.02704 0.0527 21 3.04808 0.0396 7 3.04268 0.0508 22 3.05348 0.0581 8 3.01052 0.0791 23 3.05516 0.0682 9 3.03464 0.0663 24 3.03426 0.0325 10 3.02034 0.0538 25 3.0516 0.0641 11 3.03764 0.0584 26 3.05562 0.0809 12 3.0409 0.0434 27 3.04402 0.0374 13 3.0519 0.0762 28 3.06458 0.0284 14 3.03994 0.0833 29 3.0544 0.0738 15 3.03788 0.0601
-Referring to Instruction 18-12,an R chart is to be constructed for the weight.The center line of this R chart is located at _______
(Short Answer)
4.9/5
(32)
Instruction 18-10
A supplier of silicone sheets for producers of computer chips wants to evaluate her manufacturing process. She takes a sample size of five from each day's output and counts the number of blemishes on each silicone sheet. The results from 20 days of such evaluations are presented below. She also decides that the upper specification limit is 10 blemishes.
Day 1 2 3 4 5 Mean Range 1 8 10 14 6 5 8.6 9 2 8 13 6 6 10 8.6 7 3 10 12 7 7 9 9.0 5 4 5 9 12 7 10 8.6 7 5 8 3 8 9 10 7.6 7 6 9 7 9 6 9 8.0 3 7 10 10 5 7 6 7.6 5 8 10 9 10 6 5 8.0 5 9 6 10 6 9 9 8.0 4 10 6 9 8 6 8 7.4 3 11 8 5 6 10 10 7.8 5 12 6 4 7 7 12 7.2 8 13 7 5 7 6 9 6.8 4 14 5 8 8 7 6 6.8 3 15 7 12 10 6 10 9.0 6 16 7 11 4 7 8 7.4 7 17 8 4 5 4 7 5.6 4 18 11 4 11 11 10 9.4 7 19 6 10 6 10 10 8.4 4 20 6 12 12 6 8 8.8 6
-Referring to Instruction 18-10,an R chart is to be constructed for the number of blemishes.The upper control limit for this data set is _______.
(Short Answer)
4.9/5
(34)
Instruction 18-2
A local newspaper has 10 delivery boys who each deliver the morning paper to 50 customers every day. The owner decides to record the number of papers delivered on time for a 10-day period and construct a p chart to see whether the percentage is too erratic.
Day Number of Papers Deliverd on Time 1 46 2 45 3 46 4 45 5 43 6 48 7 46 8 49 9 48 10 47
-Referring to Instruction 18-2,what is the numerical value of the lower control limit for the p chart?
(Multiple Choice)
4.8/5
(42)
In Australia,control limits on a control chart are placed so that they are three standard deviations above and below a central line.
(True/False)
4.9/5
(29)
Instruction 18-10
A supplier of silicone sheets for producers of computer chips wants to evaluate her manufacturing process. She takes a sample size of five from each day's output and counts the number of blemishes on each silicone sheet. The results from 20 days of such evaluations are presented below. She also decides that the upper specification limit is 10 blemishes.
Day 1 2 3 4 5 Mean Range 1 8 10 14 6 5 8.6 9 2 8 13 6 6 10 8.6 7 3 10 12 7 7 9 9.0 5 4 5 9 12 7 10 8.6 7 5 8 3 8 9 10 7.6 7 6 9 7 9 6 9 8.0 3 7 10 10 5 7 6 7.6 5 8 10 9 10 6 5 8.0 5 9 6 10 6 9 9 8.0 4 10 6 9 8 6 8 7.4 3 11 8 5 6 10 10 7.8 5 12 6 4 7 7 12 7.2 8 13 7 5 7 6 9 6.8 4 14 5 8 8 7 6 6.8 3 15 7 12 10 6 10 9.0 6 16 7 11 4 7 8 7.4 7 17 8 4 5 4 7 5.6 4 18 11 4 11 11 10 9.4 7 19 6 10 6 10 10 8.4 4 20 6 12 12 6 8 8.8 6
-Referring to Instruction 18-10,an R chart is to be constructed for the number of blemishes.One way to create the upper control limit involves multiplying the mean of the sample ranges by D4. For this data set,the value of D4 is _______.
(Short Answer)
4.9/5
(42)
Instruction 18-1
Below is the number of defective items from a production line over 20 consecutive morning shifts.
Day Nonconf. Day Nonconf. 1 26 11 22 2 27 12 26 3 23 13 21 4 21 14 22 5 26 15 19 6 20 16 17 7 35 17 21 8 30 18 18 9 21 19 16 10 25 20 17 Note: Nonconf. = Nonconformances
-Referring to Instruction 18-1,based on the c chart,it appears that the process is out of control.
(True/False)
4.9/5
(40)
Instruction 18-4
A manufacturer of computer disks took samples of 240 disks on 15 consecutive days. The number of disks with bad sectors was determined for each of these samples. The results are in the table that follows.
Day Bad \% Bad 1 9 0.037500 2 7 0.029167 3 4 0.016667 4 6 0.025000 5 8 0.033333 6 3 0.012500 7 6 0.025000 8 10 0.041667 9 16 0.066667 10 24 0.100000 11 15 0.062500 12 9 0.037500 13 4 0.016667 14 8 0.033333 15 6 0.025000
-Referring to Instruction 18-4,construct a p control chart for these data.
(Essay)
4.8/5
(25)
Which famous statistician developed the 14 points of management?
(Multiple Choice)
4.8/5
(41)
Instruction 18-2
A local newspaper has 10 delivery boys who each deliver the morning paper to 50 customers every day. The owner decides to record the number of papers delivered on time for a 10-day period and construct a p chart to see whether the percentage is too erratic.
Day Number of Papers Deliverd on Time 1 46 2 45 3 46 4 45 5 43 6 48 7 46 8 49 9 48 10 47
-Referring to Instruction 18-2,what is the numerical value of the upper control limit for the p chart?