Exam 10: Standard Costing: a Managerial Control Tool
Exam 1: Introduction to Managerial Accounting45 Questions
Exam 2: Basic Managerial Accounting Concepts156 Questions
Exam 3: Cost Behaviour186 Questions
Exam 4: Costvolumeprofit Analysis: a Managerial Planning Tool160 Questions
Exam 5: Job-Order Costing176 Questions
Exam 6: Process Costing157 Questions
Exam 7: Activity-Based Costing and Management155 Questions
Exam 8: Absorption and Variable Costing,and Inventory Management88 Questions
Exam 9: Budgeting, production, cash, and Master Budget166 Questions
Exam 10: Standard Costing: a Managerial Control Tool174 Questions
Exam 11: Flexible Budgets and Overhead Analysis149 Questions
Exam 12: Performance Evaluation and Decentralization145 Questions
Exam 13: Short-Run Decision Making: Relevant Costing149 Questions
Exam 14: Capital Investment Decisions153 Questions
Select questions type
Match each item with the correct statement below.
-These reflect the amount that should be paid for the quantity of input to be used.
(Multiple Choice)
4.9/5
(48)
Direct materials ( of denim per metre)
Direct labour (3 hours per hour) 18
-Refer to the Figure.What is Allan's labour rate variance?
(Multiple Choice)
4.9/5
(41)
Match the variance with its correct calculation.
-Labour rate variance
(Multiple Choice)
4.9/5
(47)
Match the variance with its correct calculation.
-Materials price variance
(Multiple Choice)
4.8/5
(42)
Acting Company has the following information: Direct Materials: Direct Labour: Standard Quantity 11,000 Standard Hours 3,000 Actual Quantity 13,000 Actual Hours 2,875 Standard Price \ 15 Standard Rate \ 12 Actual Price \ 13 Actual Rate \ 13 A. Determine the materials price variance and whether it is favourable or unfavourable.
B. Determine the materials usage variance and whether it is favourable or unfavourable.
C. Determine the labour rate variance and whether it is favourable or unfavourable.
D. Determine the labour efficiency variance and whether it is favourable or unfavourable.
(Essay)
4.8/5
(39)
Match the variance with its correct calculation.
-Budgeted costs
(Multiple Choice)
4.9/5
(33)
During August,40,000 units were produced.The standard quantity of material allowed per unit was 5 kg at a standard cost of $2.50 per kilogram.Suppose the company had a favourable usage variance of $25,000 for August.What would have been the actual quantity of materials used?
(Multiple Choice)
5.0/5
(33)
Direct materials ( of denim per metre)
Direct labour (3 hours per hour) 18
-Refer to the Figure.What is the entry to record the direct labour variances?
(Multiple Choice)
4.7/5
(41)
Ideal standards allow for machine breakdowns,slack,or momentary lack of skill.
(True/False)
4.8/5
(43)
Which of the following is NOT characteristic of direct materials variances?
(Multiple Choice)
4.8/5
(40)
Of the three cost reduction methods typically used,reverse engineering tears down the competitors' products to discover more design features that create cost reductions.
(True/False)
4.9/5
(35)
Direct materials ( 2 sheets of glass per sheet)
Direct labour (3 hours per hour) 24
-Refer to the Figure.What is the materials usage variance?
(Multiple Choice)
4.8/5
(42)
During November,10,000 direct labour hours were worked at a standard cost of $10 per hour.Suppose the direct labour rate variance for November was $4,000 unfavourable.What was the actual cost per direct labour hour?
(Multiple Choice)
4.9/5
(33)
The standard cost sheet provides the input standards needed to compute the total amount of inputs allowed for the actual output,an essential component in computing efficiency variances.
(True/False)
4.7/5
(36)
Bronze Brick Company uses the following rule to determine whether materials usage variances should be investigated:
A materials usage variance will be investigated when the variance is greater than either $5,000 or 12% of the standard cost.
During May,the company purchased and used 11,000 kg of concrete for $5 per kilogram.It was able to make 20,000 bricks.Its standard quantity of materials allowed is 0.50 kg of concrete per brick at a standard price of $6.50 per kilogram. A. Determine Bronze's material usage variance and whether it is favourable or unfavourable.
B. Should the variance be investigated?
(Essay)
4.8/5
(45)
Setting a new minimum standard is which step in the kaizen cycle of kaizen costing?
(Multiple Choice)
4.8/5
(30)
Direct materials ( 2 sheets of glass per sheet)
Direct labour (3 hours per hour) 24
-Refer to the Figure.What are Fantastic's standard hours allowed for a volume of 100,000 blades?
(Multiple Choice)
4.9/5
(33)
Direct materials ( 2 sheets of glass per sheet)
Direct labour (3 hours per hour) 24
-Refer to the Figure.What is Fantastic's labour rate variance?
(Multiple Choice)
4.8/5
(36)
Showing 101 - 120 of 174
Filters
- Essay(0)
- Multiple Choice(0)
- Short Answer(0)
- True False(0)
- Matching(0)