Exam 3: Cost Behavior
Exam 1: Introduction to Cost Management157 Questions
Exam 2: Basic Cost Management Concepts201 Questions
Exam 3: Cost Behavior200 Questions
Exam 4: Activity-Based Costing201 Questions
Exam 5: Product and Service Costing: Job-Order System150 Questions
Exam 6: Process Costing188 Questions
Exam 7: Allocating Costs of Support Departments and Joint Products173 Questions
Exam 8: Budgeting for Planning and Control Key200 Questions
Exam 9: Standard Costing: a Functional-Based Control Approach123 Questions
Exam 10: Decentralization: Responsibility Accounting, Performance Evaluation, and Transfer Pricing139 Questions
Exam 11: Strategic Cost Management151 Questions
Exam 12: Activity-Based Management146 Questions
Exam 13: The Balanced Scorecard: Strategic-Based Control124 Questions
Exam 14: Quality and Environmental Cost Management202 Questions
Exam 15: Lean Accounting and Productivity Measurement172 Questions
Exam 16: Cost-Volume-Profit Analysis138 Questions
Exam 17: Activity Resource Usage Model and Tactical Decision Making128 Questions
Exam 18: Pricing and Profitability Analysis164 Questions
Exam 19: Capital Investment126 Questions
Exam 20: Inventory Management: Economic Order Quantity, Jit, and the Theory of Constraints127 Questions
Select questions type
Figure 3-6 The Stanford Company incurred the following maintenance cost during a five month period:
Refer to Figure 3-6. Using a computer or calculator, compute the estimate of variable cost per unit of production using the method of least squares. Rounded to two decimal places, this value would be

(Multiple Choice)
4.9/5
(38)
An alternative measure of goodness of fit is the coefficient of determination.
(True/False)
4.8/5
(39)
Costs in marketing, distribution, and service after the sale __________ as number of units produced and sold __________ .
(Short Answer)
4.9/5
(26)
The three widely used quantitative methods of separating a mixed cost into its fixed and variable components are the high-low method, the scatter plot method, and the method of least squares.
(True/False)
4.9/5
(45)
Figure 3-1 Sonor Systems undertakes its own machine maintenance. The depreciation on the equipment is $20,000 per year and operating cost is $2 per machine hour. Last year 275,000 machine hours were used to produce 100,000 units.
See Figure 3-1. Develop a cost equation for the total machine maintenance cost.
(Multiple Choice)
4.9/5
(32)
Figure 3-3 The Sandoval Company has four process engineers that are each able to process 1,500 design changes. Last year 5,250 design changes were produced by the four engineers. Each engineer is paid $60,000 per year.
Refer to Figure 3-3. Calculate the activity rate per change order.
(Multiple Choice)
4.8/5
(33)
The method of least squares requires a __________ in order to be utilized.
(Short Answer)
5.0/5
(42)
Figure 3-9 Hereford Company is planning to introduce a new product with an 80 percent learning rate for production for batches of 1,000 units. The variable labor costs are $30 per unit for the first 1,000-unit batch. Each batch requires 100 hours. There are $10,000 in fixed costs not subject to learning.
Refer to Figure 3-9. What is the cumulative total time (labor hours) to produce 2,000 units based on the cumulative average-time learning curve?
(Multiple Choice)
4.8/5
(36)
When a firm acquires the resources needed to perform an activity, it is obtaining
(Multiple Choice)
5.0/5
(35)
A $4,000 per month salary paid to a supervisor is an example of a:
(Multiple Choice)
4.8/5
(35)
The Y in the equation Y = F + VX represents the __________, the dependent variable
(Short Answer)
4.9/5
(42)
Which of the following is an example of a step-fixed cost?
(Multiple Choice)
4.8/5
(27)
Assuming costs are represented on the vertical axis and volume of activity on the horizontal axis, which of the following costs would be represented by a line that starts at the origin and reaches a maximum value beyond which the line is parallel to the horizontal axis?
(Multiple Choice)
4.7/5
(34)
The level of activity performance where the amount of activity capacity needed corresponds to the level of efficiency required is called the activity capacity.
(True/False)
4.7/5
(37)
The type of resources that are acquired from outside sources, where the terms of acquisition do NOT require any long-term commitment for any given amount of the resource are called:
(Multiple Choice)
4.9/5
(42)
The __________ analysis method is a method of determining cost behavior.
(Short Answer)
4.9/5
(39)
Showing 121 - 140 of 200
Filters
- Essay(0)
- Multiple Choice(0)
- Short Answer(0)
- True False(0)
- Matching(0)