Study Set
Modern Systems Analysis and Design Study Set 1
Exam 3: Managing the Information Systems Project
Path 4
Access For Free
Share
All types
Filters
Study Flashcards
Practice Exam
Learn
Question 1
Multiple Choice
Which of the following are primary reasons for undertaking systems development projects?
Question 2
Multiple Choice
Match each of the following project management phases with the activities associated with it.(Answers may occur more than once.) -Identify and assess risk
Question 3
Multiple Choice
Match each of the following project planning activities with its corresponding definition. -Separate the entire project into manageable tasks and then logically order them to ensure a smooth evolution between tasks.
Question 4
Multiple Choice
Managing conflict within a project team to assure that conflict is not too high or too low best defines which of the following project manager activities:
Question 5
Multiple Choice
Match each of the following activities with its corresponding skills. -Defining and sequencing activities,communicating expectations,assigning resources to activities,monitoring outcomes
Question 6
Multiple Choice
Identifying,assessing,and managing the risks and day-to-day changes that occur during a project best defines which of the following project manager activities:
Question 7
Multiple Choice
Match each of the following project planning activities with its corresponding definition. -Optimistic = 1; realistic = 5; pessimistic = 9
Question 8
Multiple Choice
The responsibility for keeping all team members informed of the project status best describes the:
Question 9
Multiple Choice
Which of the following is true regarding Gantt chart construction?
Question 10
Multiple Choice
Match each of the following project management phases with the activities associated with it.(Answers may occur more than once.) -Establish a relationship with the customer
Question 11
Multiple Choice
Optimistic time is:
Question 12
Short Answer
__________ is the first phase of the project management process in which activities are performed to assess the size,scope,and complexity of the project and to establish procedures to support later project activities.
Question 13
Short Answer
A __________ is a systems analyst with a diverse set of skills-management,leadership,technical,conflict management,and customer relationship-who is responsible for initiating,planning,executing,and closing down a project.