Question 61
Multiple Choice
Which of the following is not a project planning activity?
Question 62
True/False
During the development of a preliminary schedule activity,you specify how various deliverables are produced and tested by you and your project team.
Question 63
True/False
Gantt charts typically do not show how tasks must be ordered.
Question 64
True/False
If an activity's optimistic time is 4 weeks,its realistic time is 6 weeks,and its pessimistic time is 8 weeks,then its estimated time would be 6 weeks.
Question 65
True/False
The hallway discussion project team communication method has a medium to high formality rating.
Question 66
True/False
The meeting minutes project team communication method has a low formality rating.
Question 67
True/False
The Project Scope Statement provides a detailed estimate of the project's tasks and resource requirements.
Question 68
Short Answer
__________ is the process of dividing the project into manageable tasks and logically ordering them to ensure a smooth evolution between tasks.
Question 69
Multiple Choice
Match each of the following activities with its corresponding skills. -Problem solving,smoothing out personality differences,compromising,goal setting
Question 70
True/False
Creating a work breakdown structure requires that you decompose phases into activities and activities into specific tasks.
Question 71
True/False
A slipped completion date for an activity may initiate a change to the Baseline Project Plan.
Question 72
True/False
A Project Scope Statement is developed during the project execution phase.
Question 73
Multiple Choice
Skills that include defining and sequencing activities,communicating expectations,assigning resources to activities,and monitoring outcomes best represent:
Question 74
Multiple Choice
Match each of the following project planning activities with its corresponding definition. -Optimistic = 1; realistic = 3; pessimistic = 5
Question 75
Short Answer
__________ is the amount of time that an activity can be delayed without delaying the project.
Question 76
Multiple Choice
The phase of the project management process in which activities are performed to assess the size,scope,and complexity of the project and to establish procedures to support later project activities best defines: