Question 81
Multiple Choice
The process of dividing the project into manageable tasks and logically ordering them to ensure a smooth evolution between tasks defines:
Question 82
True/False
The project workbook serves as a repository for all project correspondence,inputs,outputs,deliverables,procedures,and standards established by the project team.
Question 83
Multiple Choice
A scheduling technique where the order and duration of the sequence of activities directly affect the completion date of a project refers to:
Question 84
Multiple Choice
What would be the estimated time for completion if the time estimates for report design are as follows: optimistic = 3 weeks; pessimistic = 9 weeks; realistic = 6 weeks?
Question 85
True/False
When compared to network diagrams,Gantt charts are more useful for depicting the activities associated with large projects.
Question 86
Multiple Choice
Match each of the following project management phases with the activities associated with it.(Answers may occur more than once.) -Does not show time overlap,but shows what activities could be done in parallel.