Multiple Choice
At which point does crashing of a project cease?
A) When the project is completed
B) When no additional crashing is possible
C) When the cost to crash equals or exceeds the benefit of crashing
D) When there is zero slack.
E) When there are two critical paths.
Correct Answer:

Verified
Correct Answer:
Verified