The Manager of a National Forest Is About to Undertake

Question 37

Multiple Choice

The manager of a National Forest is about to undertake a reforestation project in a burned out area.The project will involve the following six activities: The manager of a National Forest is about to undertake a reforestation project in a burned out area.The project will involve the following six activities:   What is the estimated expected (mean) duration for project completion? A) 135 days B) 145 days C) 170 days D) 180 days E) 255 days What is the estimated expected (mean) duration for project completion?


A) 135 days
B) 145 days
C) 170 days
D) 180 days
E) 255 days