Multiple Choice
Consider a project that has an expected completion time of 50 weeks and a standard deviation of 9 weeks.What is the probability that the project is finished in 57 weeks or fewer? (Round to two decimals.)
A) 0.68
B) 0.78
C) 0.22
D) 0.32
Correct Answer:

Verified
Correct Answer:
Verified