Multiple Choice
Given an activity's optimistic, most likely, and pessimistic time estimates of 3, 5, and 13 days respectively, compute the expected time for this activity.
A) 3
B) 4
C) 5
D) 6
Correct Answer:

Verified
Correct Answer:
Verified