menu-iconExamlexExamLexServices

Discover

Ask a Question
  1. All Topics
  2. Topic
    Business
  3. Study Set
    Quantitative Analysis for Management
  4. Exam
    Exam 11: Project Management
  5. Question
    Given an Activity's Optimistic, Most Likely, and Pessimistic Time Estimates
Solved

Given an Activity's Optimistic, Most Likely, and Pessimistic Time Estimates

Question 88

Question 88

Multiple Choice

Given an activity's optimistic, most likely, and pessimistic time estimates of 4, 6, and 14 days respectively, compute the PERT expected activity time for this activity.


A) 8
B) 6
C) 7
D) 9

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Q83: Table 11-7<br>A project manager calculated early and

Q84: Table 11-7<br>A project manager calculated early and

Q85: With PERT, we are able to calculate

Q86: Table 11-9<br>A mad scientist has identified the

Q87: Table 11-7<br>A project manager calculated early and

Q89: The critical path of a network is

Q90: Table 11-1<br>The following represents a project with

Q91: The first step in planning and scheduling

Q92: CPM was developed for use in managing

Q93: Consider the following project schedule:<br> <img src="https://d2lvgg3v3hfg70.cloudfront.net/TB5481/.jpg"

Examlex

ExamLex

About UsContact UsPerks CenterHomeschoolingTest Prep

Work With Us

Campus RepresentativeInfluencers

Links

FaqPricingChrome Extension

Download The App

Get App StoreGet Google Play

Policies

Privacy PolicyTerms of ServiceHonor CodeCommunity Guidelines

Scan To Download

qr-code

Copyright © (2025) ExamLex LLC.

Privacy PolicyTerms Of ServiceHonor CodeCommunity Guidelines