Solved

Table 11-7 A Project Manager Calculated Early and Late Start and Finish

Question 83

Multiple Choice

Table 11-7
A project manager calculated early and late start and finish times for all activities in her eight-activity project but spilled her energy drink on the paper and the acid in the beverage wiped out some of the table entries.The remaining legible entries are correct.
Table 11-7 A project manager calculated early and late start and finish times for all activities in her eight-activity project but spilled her energy drink on the paper and the acid in the beverage wiped out some of the table entries.The remaining legible entries are correct.    -Consider the project summarized in Table 11-7.What is the slack for Activity C? A) 0 B) 1 C) 5 D) 7
-Consider the project summarized in Table 11-7.What is the slack for Activity C?


A) 0
B) 1
C) 5
D) 7

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions