Table 11-7 A Project Manager Calculated Early and Late Start and Finish

Question 84

Multiple Choice

Table 11-7
A project manager calculated early and late start and finish times for all activities in her eight-activity project but spilled her energy drink on the paper and the acid in the beverage wiped out some of the table entries.The remaining legible entries are correct.
Table 11-7 A project manager calculated early and late start and finish times for all activities in her eight-activity project but spilled her energy drink on the paper and the acid in the beverage wiped out some of the table entries.The remaining legible entries are correct.    -Consider the project summarized in Table 11-7.What is the early finish time for Activity E? A) 25 B) 26 C) 27 D) 28
-Consider the project summarized in Table 11-7.What is the early finish time for Activity E?


A) 25
B) 26
C) 27
D) 28

Correct Answer:

verifed

Verified