Multiple Choice
Table 11-7
A project manager calculated early and late start and finish times for all activities in her eight-activity project but spilled her energy drink on the paper and the acid in the beverage wiped out some of the table entries.The remaining legible entries are correct.
-Consider the project summarized in Table 11-7.What is the early finish time for Activity E?
A) 25
B) 26
C) 27
D) 28
Correct Answer:

Verified
Correct Answer:
Verified
Q79: Activity D of a project has a
Q80: Table 11-9<br>A mad scientist has identified the
Q81: PERT<br>A)assumes that we do not know ahead
Q82: Table 11-1<br>The following represents a project with
Q83: Table 11-7<br>A project manager calculated early and
Q85: With PERT, we are able to calculate
Q86: Table 11-9<br>A mad scientist has identified the
Q87: Table 11-7<br>A project manager calculated early and
Q88: Given an activity's optimistic, most likely, and
Q89: The critical path of a network is