Table 11-7 A Project Manager Calculated Early and Late Start and Finish

Question 87

Multiple Choice

Table 11-7
A project manager calculated early and late start and finish times for all activities in her eight-activity project but spilled her energy drink on the paper and the acid in the beverage wiped out some of the table entries.The remaining legible entries are correct.
Table 11-7 A project manager calculated early and late start and finish times for all activities in her eight-activity project but spilled her energy drink on the paper and the acid in the beverage wiped out some of the table entries.The remaining legible entries are correct.    -Consider the project summarized in Table 11-7.What is the slack for Activity D? A) 7 B) 5 C) 1 D) 0
-Consider the project summarized in Table 11-7.What is the slack for Activity D?


A) 7
B) 5
C) 1
D) 0