Table 11-7 A Project Manager Calculated Early and Late Start and Finish

Question 67

Multiple Choice

Table 11-7
A project manager calculated early and late start and finish times for all activities in her eight-activity project but spilled her energy drink on the paper and the acid in the beverage wiped out some of the table entries.The remaining legible entries are correct.
Table 11-7 A project manager calculated early and late start and finish times for all activities in her eight-activity project but spilled her energy drink on the paper and the acid in the beverage wiped out some of the table entries.The remaining legible entries are correct.    -Consider the project summarized in Table 11-7.What is the late start time for Activity G? A) 27 B) 28 C) 29 D) 30
-Consider the project summarized in Table 11-7.What is the late start time for Activity G?


A) 27
B) 28
C) 29
D) 30