Multiple Choice
Table 11-7
A project manager calculated early and late start and finish times for all activities in her eight-activity project but spilled her energy drink on the paper and the acid in the beverage wiped out some of the table entries.The remaining legible entries are correct.
-Consider the project summarized in Table 11-7.What is the early finish time for Activity D?
A) 19
B) 20
C) 21
D) 22