Multiple Choice
Table 11-2
The following represents a project with four activities.All times are in weeks.
-According to the data in Table 11-2, what is the minimum expected completion time for the project?
A) 18
B) 19
C) 37
D) 11
Correct Answer:

Verified
Correct Answer:
Verified