Multiple Choice
Table 12-3
-According to Table 12-3, there are five activities in a PERT project. What is the variance of the critical path?
A) 5.222
B) 4.222
C) 1.222
D) 0
E) 1.111
Correct Answer:

Verified
Correct Answer:
Verified