Multiple Choice
Table 12-1
The following represents a project with know activity times. All times are in weeks.
-Using the data in Table 12-1, compute the latest finish time for activity E.
A) 4
B) 10
C) 14
D) 25
E) None of the above
Correct Answer:

Verified
Correct Answer:
Verified