Multiple Choice
It may be easier to estimate the costs for ____, but as the project progresses, the project team can progressively elaborate the estimated costs as more information is known or becomes clear to allow for more accurate estimated costs.
A) near-term activities
B) activities near the end of the project
C) new activities with new procedures
D) activities with long durations
Correct Answer:

Verified
Correct Answer:
Verified