Multiple Choice
Determining the earned value involves collecting data on the percent complete for each work package and then converting this percentage to a dollar amount by multiplying the ____ of the work package by the percent complete.
A) total budgeted cost (TBC)
B) cumulative budgeted cost (CBC)
C) cumulative earned value (CEV)
D) cumulative actual cost (CAC)
Correct Answer:

Verified
Correct Answer:
Verified