    If the Total Slack Is Zero, the Activities on the Path
Solved

If the Total Slack Is Zero, the Activities on the Path

Question 114

Question 114

True/False

If the total slack is zero, the activities on the path do not need to be accelerated but cannot be delayed.

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Q109: The estimated resources required for an activity

Q110: Free slack of an activity is<br>A) the

Q111: The project control process must occur regularly

Q112: At the beginning of every project, it

Q113: The critical path of a project<br>A) cannot

Q115: The earliest finish time for an activity<br>A)

Q116: If an organization or subcontractor has performed

Q117: _ time is the latest time by

Q118: Analyzing the schedule to determine which areas

Q119: People sometimes perform to expectations, their effort

Examlex

ExamLex

About UsContact UsPerks CenterHomeschoolingTest Prep

Work With Us

Campus RepresentativeInfluencers

Links

FaqPricingChrome Extension

Download The App

Get App StoreGet Google Play

Policies

Privacy PolicyTerms of ServiceHonor CodeCommunity Guidelines

Scan To Download

qr-code

Copyright © (2025) ExamLex LLC.

Privacy PolicyTerms Of ServiceHonor CodeCommunity Guidelines