menu-iconExamlexExamLexServices

Discover

Ask a Question
  1. All Topics
  2. Topic
    Business
  3. Study Set
    Successful Project Management Study Set 1
  4. Exam
    Exam 5: Developing the Schedule
  5. Question
    The Critical Path of a Project
Solved

The Critical Path of a Project

Question 113

Question 113

Multiple Choice

The critical path of a project


A) cannot change once the project has started.
B) is the longest path in the overall network diagram.
C) always has a negative slack.
D) always has a positive slack.

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Q108: The total completion time is 25 days.Task

Q109: The estimated resources required for an activity

Q110: Free slack of an activity is<br>A) the

Q111: The project control process must occur regularly

Q112: At the beginning of every project, it

Q114: If the total slack is zero, the

Q115: The earliest finish time for an activity<br>A)

Q116: If an organization or subcontractor has performed

Q117: _ time is the latest time by

Q118: Analyzing the schedule to determine which areas

Examlex

ExamLex

About UsContact UsPerks CenterHomeschoolingTest Prep

Work With Us

Campus RepresentativeInfluencers

Links

FaqPricingChrome Extension

Download The App

Get App StoreGet Google Play

Policies

Privacy PolicyTerms of ServiceHonor CodeCommunity Guidelines

Scan To Download

qr-code

Copyright © (2025) ExamLex LLC.

Privacy PolicyTerms Of ServiceHonor CodeCommunity Guidelines