Multiple Choice
The earliest finish time for an activity
A) is calculated by adding the activity's estimated duration to its earliest start time.
B) is the same as the earliest start time of the activity's predecessor.
C) should not be delayed or would cause the project to be delayed.
D) is dependent upon the start time of its successor activities.
Correct Answer:

Verified
Correct Answer:
Verified
Q110: Free slack of an activity is<br>A) the
Q111: The project control process must occur regularly
Q112: At the beginning of every project, it
Q113: The critical path of a project<br>A) cannot
Q114: If the total slack is zero, the
Q116: If an organization or subcontractor has performed
Q117: _ time is the latest time by
Q118: Analyzing the schedule to determine which areas
Q119: People sometimes perform to expectations, their effort
Q120: The estimated duration for an activity must