Multiple Choice
When estimating resources for activities to estimate the activity's duration, the
A) availability of each resource has to be taken into account.
B) name of each resource has to be taken into account.
C) cost of each resource has to be taken into account.
D) security clearance of each resource has to be taken into account.
Correct Answer:

Verified
Correct Answer:
Verified
Q82: With respect to the project schedule, changes
Q83: Calculate the earliest start for Task D
Q84: In order to establish a basis from
Q85: The ES and EF times are determined
Q86: The amount of _ should determine the
Q88: Total slack for a project that is
Q89: When estimating the types and quantities of
Q90: The project control process starts with establishing
Q91: The _ is the estimated cost to
Q92: A regular _ should be established for