Multiple Choice
With respect to the project schedule, changes can result in any of the following except
A) the addition or deletion of activities.
B) the initial planning and sequencing of activities.
C) changes to estimated durations for specific activities.
D) a new required completion time for the project.
Correct Answer:

Verified
Correct Answer:
Verified