Multiple Choice
In order to establish a basis from which to calculate a schedule using the estimated durations for the activities, it is necessary to
A) say who has responsibility for the first task.
B) enter the tasks into a project management information system.
C) select an estimated start time and a required completion time for the overall project.
D) edit the calendars for the resources in the project management information system.
Correct Answer:

Verified
Correct Answer:
Verified