Multiple Choice
In most cases, eliminating negative slack by reducing durations of activities will involve a trade-off in the form of an increase in ____ or a reduction in ____.
A) production hours, budget
B) costs, scope
C) scope, costs
D) scope, production hours
Correct Answer:

Verified
Correct Answer:
Verified