Multiple Choice
Calculate the earliest finish for Task D if one of its predecessors, Task A, finishes on day 3, its other predecessor, Task C, finishes on day 4, and the duration of Task D is 2 days.
A) day 6
B) day 3
C) day 4
D) Cannot be calculated based upon information given.
Correct Answer:

Verified
Correct Answer:
Verified
Q16: The latest finish time of a specific
Q17: Schedule control involves four steps.Place these steps
Q18: Padding estimates with the vision of becoming
Q19: Earliest finish time (EF)is calculated _.<br>A) by
Q20: Eliminating negative slack by reducing durations of
Q22: The estimated duration for each activity must
Q23: The duration of a task is<br>A) the
Q24: The latest start time for a specific
Q25: Schedule updates of the project using actual
Q26: Agile project management is an approach to