The latest start time for a specific activity is
A) the latest time the activity can be started for the project to be completed on time.
B) always equal to the activity's earliest finish time.
C) dependent upon the predecessor's latest finish time.
D) same as the latest finish time of the activity's successor activities.
Correct Answer:

Verified
Correct Answer:
Verified