Multiple Choice
Eliminating negative slack by reducing durations of activities will involve a trade-off in the form of
A) no change in costs and an increase in scope.
B) a decrease in costs and an expansion in scope.
C) an increase in costs or a reduction in scope.
D) an decrease in costs and no change in scope.
Correct Answer:

Verified
Correct Answer:
Verified