Multiple Choice
If the total slack for a project is 4 days, this means
A) the activities on the path can be delayed a total of four days and the project still could be completed on time.
B) the activities on the path must be accelerated by four days for the project to be completed on time.
C) all the activities must be accelerated by four days for the project to be completed on time.
D) all the activities can be delayed by four days and the project still be completed on time.
Correct Answer:

Verified
Correct Answer:
Verified
Q3: The _ involves regularly gathering data on
Q4: The key to effective project control is
Q5: The earliest start time for an activity
Q6: Having the person who will be responsible
Q7: Latest finish time (LF)is the latest time
Q9: It is important to know what types
Q10: Throughout the performance of the project, some
Q11: The development team develops, delivers, and demonstrates
Q12: A concentrated effort to accelerate project progress
Q13: The project control process starts with establishing