Multiple Choice
The key to effective project control is measuring actual progress and comparing it to planned progress on a timely and regular basis and
A) taking any needed corrective action immediately.
B) leaving the project to self-correct.
C) fast tracking all the activities in the project until the project is ahead of schedule.
D) making sure the critical path doesn't change.
Correct Answer:

Verified
Correct Answer:
Verified