Multiple Choice
The ____ involves regularly gathering data on project performance, comparing actual performance to planned performance, and taking corrective actions if actual performance is behind planned performance.
A) rational unified process
B) project control process
C) network-based planning process
D) work breakdown structure
Correct Answer:

Verified
Correct Answer:
Verified