Multiple Choice
Having the person who will be responsible for performing a specific activity estimate the duration for that activity ____ from that person and ____ that may be introduced by having one person estimate the durations for all of the activities.
A) takes more effort, creates a problem
B) gives the status of the project, sets best practices
C) generates a commitment , avoids any bias
D) elevates the placement perception, creates errors