Multiple Choice
Slack time in a network is the
A) amount of time that an activity would take assuming very unfavorable conditions.
B) shortest amount of time that could be required to complete the activity.
C) amount of time that you would expect it would take to complete the activity.
D) difference between the expected completion time of the project using pessimistic times and the expected completion time of the project using optimistic times.
E) amount of time that an activity can be delayed without delaying the entire project.
Correct Answer:

Verified
Correct Answer:
Verified
Q51: In PERT analysis, how is the pessimistic
Q56: Before drawing a PERT or CPM network,
Q59: An IT project requires 6 activities.The table
Q60: Given an activity's optimistic,most likely,and pessimistic time
Q61: Table 11-6 <img src="https://d2lvgg3v3hfg70.cloudfront.net/TB2950/.jpg" alt="Table 11-6
Q63: Slack is the time an activity can
Q64: Which of the following is not a
Q65: Table 11-5 <img src="https://d2lvgg3v3hfg70.cloudfront.net/TB2950/.jpg" alt="Table 11-5
Q67: Table 11-6 <img src="https://d2lvgg3v3hfg70.cloudfront.net/TB2950/.jpg" alt="Table 11-6
Q114: One PERT/COST assumption is that money is