Multiple Choice
If a project activity experiences positive variation:
A) the following activity usually begins immediately on completion of its predecessor.
B) the variation is usually passed downstream to the immediate follower.
C) the variation is usually passed downstream to the most critical activity.
D) the variation is usually not passed downstream.
Correct Answer:

Verified
Correct Answer:
Verified
Q19: A project consists of six consecutive tasks
Q20: A project is represented by the activity
Q21: Keith welds a one-fourth-inch diameter ball bearing
Q22: A project is represented by the activity
Q23: The Central Limit Theorem says that if
Q25: Under the student syndrome model,the slope of
Q26: The root cause of overinflated time estimates
Q27: In classic project management,activity durations are estimated
Q28: Create and solve an example of at
Q72: An important element in critical chain scheduling