Multiple Choice
A project has the precedence requirements and activity durations shown in the table. After he draws the network, the project manager decides that activities B, C, and D can be represented by a hammock activity. What are the early start and late finish times associated with this hammock activity?
A) 11, 30
B) 7, 24
C) 11, 24
D) 7, 36