    When Developing a Project Schedule,float (Or Slack)refers to the Time
Solved

When Developing a Project Schedule,float (Or Slack)refers to the Time

Question 40

Question 40

True/False

When developing a project schedule,float (or slack)refers to the time between the start and the finish of a planned activity.

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Q1: A successor activity follows a predecessor activity

Q2: <img src="https://d2lvgg3v3hfg70.cloudfront.net/TB6636/.jpg" alt=" Figure 7-2 Research

Q13: <img src="https://d2lvgg3v3hfg70.cloudfront.net/TB6636/.jpg" alt=" Figure 7-5 Duration

Q21: In order for activities to be useful

Q22: <img src="https://d2lvgg3v3hfg70.cloudfront.net/TB6636/.jpg" alt=" Figure 7-2 Research

Q25: Despite the insights that PERT provides,there are

Q34: <img src="https://d2lvgg3v3hfg70.cloudfront.net/TB6636/.jpg" alt=" Figure 7-1 Assembly

Q40: <img src="https://d2lvgg3v3hfg70.cloudfront.net/TB6636/.jpg" alt=" Figure 7-6 Network

Q43: All of the following strategies can help

Q45: All of the following items can provide

Examlex

ExamLex

About UsContact UsPerks CenterHomeschoolingTest Prep

Work With Us

Campus RepresentativeInfluencers

Links

FaqPricingChrome Extension

Download The App

Get App StoreGet Google Play

Policies

Privacy PolicyTerms of ServiceHonor CodeCommunity Guidelines

Scan To Download

qr-code

Copyright © (2025) ExamLex LLC.

Privacy PolicyTerms Of ServiceHonor CodeCommunity Guidelines