Multiple Choice
All of the following strategies can help a project team to develop realistic time estimates for project activities EXCEPT:
A) adding a significant buffer to each activity
B) be sure to consider learning curves, interruptions and competing priorities
C) adjust estimates from previous projects to account for differences
D) verify the time estimates with the people doing the work
Correct Answer:

Verified
Correct Answer:
Verified
Q1: A successor activity follows a predecessor activity
Q2: <img src="https://d2lvgg3v3hfg70.cloudfront.net/TB6636/.jpg" alt=" Figure 7-2 Research
Q13: <img src="https://d2lvgg3v3hfg70.cloudfront.net/TB6636/.jpg" alt=" Figure 7-5 Duration
Q25: Despite the insights that PERT provides,there are
Q34: <img src="https://d2lvgg3v3hfg70.cloudfront.net/TB6636/.jpg" alt=" Figure 7-1 Assembly
Q40: When developing a project schedule,float (or slack)refers
Q45: All of the following items can provide
Q45: <img src="https://d2lvgg3v3hfg70.cloudfront.net/TB6636/.jpg" alt=" Figure 7-6 Network
Q46: All of the following problems contribute to
Q48: PERT refers to the Program Evaluation and